NOTICE OF ROAD CONSTRUCTION

Milling & Paving Construction Project
on Rte. 156 in East Haddam to Old Lyme
Tentative Start and Ending Dates:
June 1, 2020 through July 22, 2020

The Connecticut Department of Transportation will commence a milling and paving project on Rte. 156, Monday, June 1, 2020.  This project, which will mill and pave 8.44 miles of the road from East Haddam to Old Lyme will start with milling and continue through June 23.  Roadway paving will then begin July 7 and continue through July 22.

Motorists can expect lane closures on Rte. 156 beginning at Rte, 82 in East Haddam through Lyme, ending on Rte. 1 in Old Lyme.  The regular work schedule for this project will be 7:00 a.m. to 5:00 p.m., Monday through Friday.

Drivers should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions.

Motorists are also requested to maintain a safe speed while driving in the construction area or when approaching it.

    